Units 1 – 5 Maxted Court

Following the oil depot explosion at the Buncefield depot we were asked to attend site, initially to make these buildings safe. The existing tenants largely remaining in place whilst the repair works were carried out. We then undertook extensive surveys and investigations and negotiations with our Client and their insurers to return these units to their former condition.

The units are steel framed and clad with asbestos sheet roofing, metal sheet and curtain walling to elevations, with a large office content. The works were limited to minor steelwork repairs, re-roofing and replacement of all damaged external cladding.

  • F&C Property Asset Management
  • £3,934,000
  • Design and Build
  • Norman Rourke Pryme
  • DP Architects
  • Norman Rourke Pryme
  • Chamberlain Consulting
  • N/A